A project plan gives you a working estimate of how much time, effort, and money the work will take. Its usefulness depends on how clearly you explain the assumptions behind it and how quickly you update it when those assumptions change.
In The Fundamental Ambiguity of Being Human, published in Tricycle, Pema Chödrön reflects on how strongly we look for certainty when things are changing. Project managers face a version of that tension every time a sponsor asks for a firm date while requirements, staffing, or dependencies are still unsettled.
This article continues our series on VUCA, which stands for volatility, uncertainty, complexity, and ambiguity. The four reinforce each other. A supplier’s lead time may change suddenly, an approval requirement may be unclear, and a delay in one project may affect several others. Each makes the outcome harder to predict.
Make uncertainty visible
Start by separating what you know from what you’re assuming and what you still need to find out. A signed contract may establish the delivery date. The availability of a specialist may still be an assumption. The effort required for a migration may remain unknown until the team tests a sample. Leave room to respond to events you can’t yet anticipate.
It takes courage to raise uncertainty when a client, regulator, or sponsor expects a fixed date and budget. Give stakeholders a forecast they can act on by explaining what currently looks achievable, what has to be true for it to happen, and when you’ll know more.
For example, “We’re forecasting a June launch if testing starts by May 12. If the test environment is late, we’ll bring you options for phasing the release or moving the date.” That gives stakeholders a commitment to review the situation and a clear trigger for action.
Plan realistically and show the range
A single estimate can be useful for building a working schedule. A range gives stakeholders a better sense of how much the outcome could vary. Start with the most likely estimate, then ask what would have to happen for the work to finish sooner or take longer.
- Use three-point estimates where uncertainty matters. Estimate optimistic, most likely, and pessimistic outcomes. PERT combines those estimates into a weighted expected duration for use in planning.
- Use simulation for decisions that justify the extra effort. Monte Carlo simulation can model many possible schedule or cost outcomes based on the ranges and assumptions you supply.
- Keep smaller projects practical. A discussion of best-case, most likely, and worst-case scenarios may give the team enough information to choose a contingency and agree on when to use it.
Use project scheduling and dependencies to identify which downstream milestones could move if an estimate changes. Where the uncertainty involves shared people or skills, use cross-project capacity planning to compare staffing and start-date options before making a new commitment.
Update the forecast as you learn
Keep a risk register and review it as work progresses. Give each significant risk an owner, an agreed response, and a trigger for action. When a risk becomes an issue, record what happened and update the forecast using current conditions.
In stakeholder updates, show what changed, why it changed, what you now expect, and whether a decision is needed. Keep the approved baseline available for comparison. Use project and portfolio reporting to share the right level of detail with delivery teams, sponsors, and executives.
See how uncertainty affects other projects
Suppose testing is likely to run two weeks late and the same specialist is booked on another project. Compare the choices before moving anyone. Could you phase the release, shift the second project, or add temporary capacity? Show what each option means for cost, delivery dates, and the business outcomes both projects support.
That’s where Strategic Portfolio Management helps. Project Insight connects schedules, staffing, costs, and priorities so leaders can see what’s at stake across projects and make a decision before teams commit to a revised plan.
The Project Data Backbone guide series explains which project records to connect so those forecasts and trade-offs are grounded in the work teams are actually doing.
Explore Strategic Portfolio Management
About the author
Adapted from the original article by George Pitagorsky, PMP. George brings mindfulness, people-centered systems, and process thinking to project management. His books include Managing Expectations: A Mindful Approach to Achieving Success, The Zen Approach to Project Management, Managing Conflict in Projects, and PM Foundation. He is a senior teacher at the NY Insight Meditation Center.