How Do You Calculate Earned Value? A Worked Example

To calculate earned value (EV), multiply the approved budget for a task by the percentage of work completed, if your project measures progress by percent complete. For a task budgeted at $1,600, 50% completion earns $800 of value. Compare that $800 with the value you planned to earn by the same date and what it actually cost to get there.

What is the difference between planned value, earned value, and actual cost?

  • Planned value (PV). The budgeted cost of the work scheduled through the reporting date.
  • Earned value (EV). The budgeted cost of the work completed through that date.
  • Actual cost (AC). What the completed work has cost to date.

Use the same reporting date for all three figures. The full task budget is $1,600 in the example below. At the end of day one, the plan calls for half the work to be complete, so planned value at that point is $800.

How do you calculate cost and schedule variance?

  • Cost variance (CV) = EV − AC. A negative result means the work performed has cost more than budgeted.
  • Schedule variance (SV) = EV − PV. A negative result means the team has completed less work than planned by the reporting date, measured in budget terms.

Schedule variance shows the value of work ahead of or behind plan. To see whether the finish date will move, check the remaining effort, dependencies, and team availability.

Worked example: Four ways the same task could go

You budget 16 developer hours at $100 per hour and spread the work evenly over two days. At the end of day one, you expected eight hours’ worth of work to be complete, so PV is $800. Assume the developer’s actual cost is also $100 per hour. For each scenario, the team reports how much work is complete and estimates the hours still needed.

Day-one results for a $1,600 task with $800 in planned value
Scenario Complete Actual cost Earned value Schedule variance Cost variance
1. On plan 50% $800 $800 $0 $0
2. Behind plan, on cost 37.5% $600 $600 −$200 $0
3. On schedule, under cost 50% $600 $800 $0 +$200
4. Behind plan, over cost 37.5% $1,000 $600 −$200 −$400

What does each scenario tell you about the finish?

To forecast the final cost, add actual cost to the estimated cost of the remaining work. In this example, the remaining cost is the developer’s estimated remaining hours multiplied by $100.

  1. On plan. The developer spent eight hours, completed half the work, and expects to need eight more hours. The forecast is $1,600, with a day-two finish if those hours are available.
  2. Behind plan, on cost. The developer spent six hours and needs ten more. The forecast is still $1,600, but finishing on day two requires ten available hours. Check capacity before confirming the date.
  3. On schedule, under cost. The developer completed half the work in six hours and expects to need six more. The forecast is $1,200. Earned value is $800 at the day-one cutoff because half the budgeted work is complete.
  4. Behind plan, over cost. The developer spent ten hours and estimates ten more. The forecast is $2,000, or $400 over the task budget. Find out what’s driving the extra effort and check whether dependent work will need to move.

Use earned value to decide where to act

On a larger project, roll up planned value, earned value, and actual cost to see overall performance. Then look at the tasks driving the biggest variances. A favorable total can hide a delay on a task that controls the finish date, so review the schedule alongside the financial figures.

In Project Insight, the Project Budgeting add-on supports planned value and earned value calculations. Use project budgeting and cost forecasting to review performance alongside current costs and remaining work.

At the portfolio level, a recovery decision can affect more than one project. If a late task needs a specialist already booked elsewhere, compare the impact on both schedules and budgets before moving the assignment. That’s how task-level performance data supports Strategic Portfolio Management.

Read the Project Financial Tracking Playbook


About the author

Adapted from the original article by Patti Cardiff, a project management consultant with more than 15 years of experience managing complex website projects. Her clients span software development, healthcare, and professional organizations. Connect with Patti Cardiff on LinkedIn.